Optimizing New York's Reforming the Energy Vision

Frank Felder, Rasika Athawale

Research output: Contribution to journalArticle

Abstract

Parallel to other efforts worldwide, the State of New York's Reforming the Energy Vision (NY REV) is an ambitious initiative of the Governor and the Public Service Commission to fundamentally reorient the structure of the State's power sector from a primarily centralized model to a highly decentralized one. Its success depends on the Distribution System Implementation Plan (DSIP), which in turn depends on which proposals for providing distributed energy resources (DERs) and utility distribution assets are selected to constitute the plan. The selection approach uses a benefit-cost analysis (BCA), which will not be sufficient to achieve an optimal DSIP. Instead, an optimization approach should be utilized and phased in to ensure timely success of this regulatory initiative.

Original languageEnglish
JournalUtilities Policy
DOIs
Publication statusAccepted/In press - 2016

Fingerprint

distribution system
energy
cost-benefit analysis
public service
energy resource
assets
resources
plan
Distribution system
System implementation
Energy
Public services
Energy resources
Benefit-cost analysis
Assets
distribution

Keywords

  • Benefit-cost analysis
  • Distributed energy resources
  • New York Reforming the Energy Vision
  • Optimization

ASJC Scopus subject areas

  • Business and International Management
  • Development
  • Law
  • Sociology and Political Science
  • Management, Monitoring, Policy and Law

Cite this

Optimizing New York's Reforming the Energy Vision. / Felder, Frank; Athawale, Rasika.

In: Utilities Policy, 2016.

Research output: Contribution to journalArticle

@article{e2684b6873104db68c91a9e878433b66,
title = "Optimizing New York's Reforming the Energy Vision",
abstract = "Parallel to other efforts worldwide, the State of New York's Reforming the Energy Vision (NY REV) is an ambitious initiative of the Governor and the Public Service Commission to fundamentally reorient the structure of the State's power sector from a primarily centralized model to a highly decentralized one. Its success depends on the Distribution System Implementation Plan (DSIP), which in turn depends on which proposals for providing distributed energy resources (DERs) and utility distribution assets are selected to constitute the plan. The selection approach uses a benefit-cost analysis (BCA), which will not be sufficient to achieve an optimal DSIP. Instead, an optimization approach should be utilized and phased in to ensure timely success of this regulatory initiative.",
keywords = "Benefit-cost analysis, Distributed energy resources, New York Reforming the Energy Vision, Optimization",
author = "Frank Felder and Rasika Athawale",
year = "2016",
doi = "10.1016/j.jup.2016.04.006",
language = "English",
journal = "Utilities Policy",
issn = "0957-1787",
publisher = "Elsevier BV",

}

TY - JOUR

T1 - Optimizing New York's Reforming the Energy Vision

AU - Felder, Frank

AU - Athawale, Rasika

PY - 2016

Y1 - 2016

N2 - Parallel to other efforts worldwide, the State of New York's Reforming the Energy Vision (NY REV) is an ambitious initiative of the Governor and the Public Service Commission to fundamentally reorient the structure of the State's power sector from a primarily centralized model to a highly decentralized one. Its success depends on the Distribution System Implementation Plan (DSIP), which in turn depends on which proposals for providing distributed energy resources (DERs) and utility distribution assets are selected to constitute the plan. The selection approach uses a benefit-cost analysis (BCA), which will not be sufficient to achieve an optimal DSIP. Instead, an optimization approach should be utilized and phased in to ensure timely success of this regulatory initiative.

AB - Parallel to other efforts worldwide, the State of New York's Reforming the Energy Vision (NY REV) is an ambitious initiative of the Governor and the Public Service Commission to fundamentally reorient the structure of the State's power sector from a primarily centralized model to a highly decentralized one. Its success depends on the Distribution System Implementation Plan (DSIP), which in turn depends on which proposals for providing distributed energy resources (DERs) and utility distribution assets are selected to constitute the plan. The selection approach uses a benefit-cost analysis (BCA), which will not be sufficient to achieve an optimal DSIP. Instead, an optimization approach should be utilized and phased in to ensure timely success of this regulatory initiative.

KW - Benefit-cost analysis

KW - Distributed energy resources

KW - New York Reforming the Energy Vision

KW - Optimization

UR - http://www.scopus.com/inward/record.url?scp=84965125909&partnerID=8YFLogxK

UR - http://www.scopus.com/inward/citedby.url?scp=84965125909&partnerID=8YFLogxK

U2 - 10.1016/j.jup.2016.04.006

DO - 10.1016/j.jup.2016.04.006

M3 - Article

JO - Utilities Policy

JF - Utilities Policy

SN - 0957-1787

ER -